Campus parking lot, Lovers Lane closures beginning June 12

$
0
0

Several construction projects will begin June 12 on K-State’s Manhattan campus.

• Lovers Lane will be closed to all traffic from 6 a.m. Monday, June 12, to 5 p.m. Tuesday, June 13, so workers can remove two old roof mounted chillers from Bluemont Hall.

• The west circle parking lot of Anderson Hall will be closed from 6 a.m. Monday, June 12, to 5 p.m. Friday, June 16. Workers will be removing the old chiller in the parking lot.

• The south half of the D1 parking lot, west of Memorial Stadium, will be closed beginning at 7 a.m. Monday, June 12, so workers can reconstruct the parking lot. Work is scheduled to be complete in late July.

Contact Jack Carlson at 785-532-1722 with any questions.